As required in Regulation (EU) 2017/459 (NC CAM), GTS has performed a market demand assessment between 1 July and 25 August 2019 to gain insight in the need for additional capacity demand from market parties at the interconnection points. 
The results of the demand assessment have been translated into concrete proposals by the involved TSO’s to increase capacity
Today we published the documents that contain these proposals as part of the formal consultation that will end 1 October 2020. We invite you to share your views with us at [email protected]
The additional capacity based on the outcome of this consultation and approval of the regulators, will be offered in the 2021 annual yearly capacity auction at Prisma.