Availability quality conversion

31 May 2018 19:11

The amount of available nitrogen for quality conversion is reduced to 502.000 m3/h. This reduction is not announced in the Maintenance Calendar and is the consequence of a failure or gastransport related circumstances. The expectation is that 50.000 m3/h nitrogen is available within 2 days.

Message data
messageType other
messageId GTS21X-NL-A-A0A0A-Z-000719_002
eventStatus Inactive
eventStart 2018-05-30 07:15:00
eventStop 2018-05-30 19:00:00
publicationDateTime 2018-05-31 19:11:07
remarks
marketParticipant(s) Gasunie Transport Services B.V. - 21X-NL-A-A0A0A-Z